```kroki {_type=plantuml}
@startgantt
[Task1] requires 10 days
then [Task2] requires 4 days
-- Phase Two --
[Task3] starts 5 days after [Task2]'s end and requires 5 days
then [Task4] requires 6 days
[Review 01] happens on 2 days after [Task2]'s end
Separator just at [Task1]'s end
Separator just 2 days before [Task3]'s start
@endgantt
```